Wixom Industrial One, LLC v. City of Wixom (Michigan Data Center Moratorium Suit)
Wixom Industrial One sued the City of Wixom in federal court, alleging the city used its site plan to draft rules that would block a 519,400-square-foot data center on 54 acres zoned for the use.
Wixom Industrial One, LLC sued the City of Wixom, Michigan on August 7, 2026 in the U.S. District Court for the Eastern District of Michigan (No. 2:26-cv-12754), alleging the city violated Michigan's zoning act, WHMI reported, citing Crain's Detroit. The developer says the city used its rough site plan for a three-building, 519,400-square-foot data center campus on 54 acres on South Wixom Road to write restrictive ordinances. The city had adopted a six-month moratorium on data center development and in July rejected a proposed waiver.
Why it matters
The case tests whether a city can respond to opposition to one pending data center proposal with a moratorium and new rules for the use. The developer's claim rests on its allegation that the city drew the ordinances from its own site plan.
Part of the Data Center Litigation Tracker: every related matter in one table.
Full write-up
Wixom Industrial One, LLC filed suit against the City of Wixom on August 7, 2026 in the U.S. District Court for the Eastern District of Michigan, alleging the city violated the state's zoning act, WHMI reported, citing Crain's Detroit. The complaint seeks declaratory judgment, injunctive relief and damages, according to the court docket (No. 2:26-cv-12754, assigned to Judge Robert J. White).
The property is 54 acres on South Wixom Road north of Interstate 96, assembled for an industrial park by the company's developer according to WHMI. After Missouri real estate firm Sansone Group approached the developer, the site was pitched for a data center. Exhibits to the complaint identify the site as 30625 S. Wixom Road and include a city email stating that the parcel is zoned M-1, Light Industrial. The city adopted a six-month moratorium on data center development after public sentiment shifted, and in July the City Council rejected a proposed waiver from it.
The developer alleges the city used its rough site plan for a three-building, 519,400-square-foot campus to write ordinances that would effectively bar data center development on property zoned for it, and it describes itself as the victim of a council more concerned with public opinion than with the law, according to WHMI. The article did not include a response from the city. The docket shows the city filed a motion to dismiss on September 1, Wixom Industrial One filed an amended complaint on October 6, the city filed another motion to dismiss on October 20, and the developer responded on November 10.
Case timeline
Keep reading, free
You've used this month's free write-ups. A free account reads every write-up and timeline with no limit and adds email alerts. Just your email, no password.
Email me when the court rules
We check this federal docket every day and send one email when an order, judgment, dismissal or closing appears. Free account; stop any time.
Facing a dispute like this one? Estimate its value with the free Case Value Calculator or read what a zoning or land-use claim is worth.
Looking for something else?
More zoning & land use matters
Other matters in Michigan
Recently added
CREdocket summarizes public court records and reporting; see our sourcing standards and corrections log. Not legal advice. Facing something similar? Contact us.