Center for Biological Diversity Sues New Mexico Office of the State Engineer Over Emergency Water Authorization for Project Jupiter Data Center Construction
The Center for Biological Diversity sued New Mexico's Office of the State Engineer over an October 2025 emergency authorization letting groundwater be used to build the 1,400-acre Project Jupiter data center; it seeks a pause in water use.
The Center for Biological Diversity sued the New Mexico Office of the State Engineer on Nov. 19, 2026 in the 1st Judicial District Court, the Albuquerque Journal reported. The suit challenges an emergency authorization the state engineer granted in October 2025 to Santa Teresa Capital LLC, the company that owns the water rights, and demands a pause in water use at the Project Jupiter construction site in Doña Ana County.
Why it matters
The suit asks a court to pause the water supply for construction of a hyperscale data center that is already being built. It follows a state Supreme Court petition by the same group that was denied in September.
Part of the Data Center Litigation Tracker: every related matter in one table.
Full write-up
The Center for Biological Diversity filed suit on Thursday, Nov. 19, 2026 in New Mexico's 1st Judicial District Court against the Office of the State Engineer and the state engineer, the Albuquerque Journal reported. The group's press release says the case was filed in Santa Fe County District Court and that it demands a pause in water use at the construction site until all legally mandated requirements are met.
According to the Journal, the state engineer in October 2025 granted Santa Teresa Capital LLC, the company that owns the water rights, an emergency authorization tied to water used to irrigate a sod farm near the site of the 1,400-acre data center. The complaint says Project Jupiter's construction has used 195 million gallons of fresh water over the past year. The lawsuit alleges the state engineer violated the beneficial use requirement, and the center said in a statement quoted by the Journal that before approving a change in use the state engineer must provide public notice. The Journal reported the project is under construction by Stack Infrastructure and BorderPlex Digital Assets and that Oracle Corp. plans to lease and operate the data center.
The Office of the State Engineer did not immediately respond to the Journal's request for comment. The Santa Fe New Mexican reported that an attorney for Santa Teresa Capital dismissed the lawsuit as a repetition of the claims the group made to the state Supreme Court earlier this year; she said the company’s water right has been permitted for commercial and industrial use for more than 40 years and that the only change was the replacement of a failed well with one drawing from the same aquifer at the same limits. The New Mexican reported that a spokesperson for the Office of the State Engineer declined to respond to the allegations, although the agency’s attorneys have defended the permit and emergency authorization as legal in recent months. The Journal reported that in September the New Mexico Supreme Court denied the center's petition challenging the emergency authorization.
Case timeline
Keep reading, free
You've used this month's free write-ups. A free account reads every write-up and timeline with no limit and adds email alerts. Just your email, no password.
The CRE Distress Brief, every Monday
This week: 54 new commercial real estate lawsuits, plus the week's bankruptcies, CMBS defaults and foreclosure postings, charted. Free; unsubscribe in one click. See what's inside.
Facing a dispute like this one? Estimate its value with the free Case Value Calculator or read what a contamination claim is worth.
Looking for something else?
More environmental matters
Other matters in New Mexico
Recently added
CREdocket summarizes public court records and reporting; see our sourcing standards and corrections log. Not legal advice. Facing something similar? Contact us.