Date
October 15, 2026
Added to tracker
October 16, 2026
Court or forum
Appellate Division of the Supreme Court of the State of New York, First Department
State
New York
Amount / scale
$1,396,058.74 judgment vacated and remitted for recalculation of damages
Parties
Plaintiff-Respondent (Supplier/Lien Claimant): Waterworks Operating Co., LLCDefendant-Appellant (Owner): 514 West 24th Owner LLCNon-Party Construction Manager: Sunrise Construction, LLC

New York's Appellate Division, First Department, on October 15, 2026 affirmed liability but vacated a roughly $1.4 million mechanic's-lien and breach-of-contract judgment that bathroom-fixtures supplier Waterworks Operating Co. won against 514 West 24th Owner LLC over unpaid materials delivered to a Chelsea redevelopment project. The court rejected the Owner's argument that an unauthorized construction manager's change orders could not bind it, but found Waterworks' proof of $237,069 of the claimed damages improperly relied on a reply-only affidavit, and remitted the case to Supreme Court to recalculate damages.

Why it matters

The ruling is a reminder to commercial developers and contractors that winning on liability in a mechanic's-lien or construction-payment dispute does not guarantee the damages figure survives appeal if any portion of the proof was submitted at the wrong procedural moment. It also signals that an owner's silent acceptance of materials delivered under a change order can ratify that change order even where a construction manager arguably lacked authority to approve it under the governing agreement.

Weekly email

New on CREdocket, every Monday

The week's new commercial real estate lawsuits, rulings in cases we follow, and market signals. Free; unsubscribe in one click.

Waterworks Operating Company, a manufacturer and supplier of high-end bathroom and cabinet fixtures, sued 514 West 24th Owner LLC and its surety in New York County Supreme Court over unpaid bills for materials delivered to the Owner's redevelopment of a building in Chelsea. Under a series of purchase orders and change orders, the Owner had agreed to pay a full contract price of $2,577,166.99. The parties agreed the Owner had paid $1,608,827.37 for goods actually delivered and accepted, leaving Waterworks to file a mechanic's lien for the remaining $968,339.62 it says it was owed.

Case timeline · 3 entries Latest: October 15, 2026 — First Department affirms liability, vacates the judgment, and remits for recalculation of damages

Free · no account needed

Keep reading

Read the full write-up and case timeline. Up to 10 a month are free without an account; a free account is unlimited and adds email alerts.

Read the full write-up

Or create a free account with just your email:

Alerts

Get an email when new construction defect matters in New York are filed

Case Value Calculator · Beta

What's this Construction Defect case worth?

Describe your own facts and get a damages-range estimate grounded in real cited case law.

Try the calculator
Share LinkedIn Email

More construction defect matters

Other matters in New York

Recently added

CREdocket summarizes public court records and reporting; see our sourcing standards and corrections log. Not legal advice. Facing something similar? Contact us.